Unequal rises[1]
The foot expects the same height on every step: one step higher or lower, often the first or the last, trips people.
Divide the total rise into equal heights with the calculator and measure each step before gluing the tread.

| Material | Quantity |
|---|---|
| MG-20 (0-20 mm crushed stone) | 720 kg |
| Riser blocks | 36 pieces |
| Tread slabs | 1.8 m² (19.2 sq ft) |
| 20 mm clear stone (fill) | 50 kg |
| Concrete adhesive (825 ml cartridges) | 1 cartridge |
The total and each step's time come from the same calculation as the estimator: the steps plus machine learning add up to the total. Planning steps (locate request, permits) keep the guide's fixed time.
Three rules guide the design:
The calculator starts from the total rise and gives the number of steps, their equal rise, the run and the total length.
Done when : You have the total rise to within 5 mm, the available length and width, and the calculator proposes equal steps that meet the rise, run and stride rules in that space.
Done when : The calculator gives equal steps with the chosen product, with no flagged mismatch between block height and rise.
Block or slab steps set on gravel and not attached to the house are landscaping: the RBQ says no licence is required to build them. Steps attached to the building or poured on footings touch the building and need a licensed business.
When the stair serves the house entrance, the code rules apply: uniform rises, a minimum run, a handrail beyond three risers and a guard where the walking surface is more than 600 mm above the ground beside it. Your municipality may have its own exceptions. Before you dig, file your Info-Excavation request.
Done when : You know whether the steps float or are attached, which code rules apply, whether a permit is required, and where any required handrail or guard will go.
Done when : You have a valid request number and all marks or clearances before you dig.
Done when : The materials are delivered where planned, counted and with no broken slab.
Steps are built before the paving around them, so the adhesive has set when the plate compactor passes close by. Dig the step footprint, a little wider than the blocks, to the base depth plus one buried course of blocks under the first step. The calculator gives the footprint and the volume.
Done when : The footprint is marked on the ground, centred on the door, and the height reference is carried to the foot of the steps.
Safety : Never look into the rotating laser beam or aim it at anyone's eyes. Set the tripod on firm ground, out of the way of traffic.
Done when : The bottom is flat, firm and at the planned depth over the whole footprint, checked with a level and a tape.
Safety : Dig by hand within 1 m of the marks. Gloves and safety boots; bend your knees to lift soil.
The compacted crushed stone base keeps the steps from settling and moving with frost. Unilock gives 100 to 150 mm of compacted gravel under block steps; on clay or silt we plan thicker. The stone is compacted in thin lifts with a plate compactor.
Done when : The base is level both ways, at the planned height, and no longer marks under a heel or under the plate.
Safety : Hearing protection and steel-toe boots with the plate compactor.
A block step is a small box: glued blocks for the riser and sides, a compacted clear stone fill and a glued slab tread with a slight overhang. Each step rests on the box of the step below, and the first sits on a buried course. Precast monolithic or natural stone steps go in the same way, one piece per step, on a compacted base.
Done when : Measured with a tape, every rise is equal, with no more than 5 mm between two steps; each tread falls slightly forward; nothing moves underfoot after the set time.
Safety : Lift slabs with two people. When cutting, wear glasses, hearing protection and a dust mask.
Done when : The paving butts the steps with no gap, no step moved during compaction and a joint separates the steps from the building.
Done when : The required handrail or guard is in place, does not move when you lean on it with your full weight and meets the code height.
Safety : Drilling or cutting concrete: glasses, hearing protection and a dust mask.
The foot expects the same height on every step: one step higher or lower, often the first or the last, trips people.
Divide the total rise into equal heights with the calculator and measure each step before gluing the tread.
The foot does not fit on the step: people go down on their heel or toe, especially in winter.
Keep the run between 280 and 425 mm, at least 255 mm where the code applies; if space is short, add a landing.
The plate compactor runs against steps whose adhesive has not set and moves them.
Build the steps first and let the adhesive set before compacting the paving around them.
Water sits on the step and freezes: ice forms there first.
Give each tread a slight forward fall.
The house does not move but floating steps rise and fall with frost: the joint breaks and the steps crack.
Either the steps float and stay separated from the building by a joint, or they sit on footings below frost built by a licensed business.
A step under 100 mm goes unnoticed and trips people.
Replace it with a gentle ramp or regroup the rise to get steps of at least 100 mm.
The first step slides or sinks and drags the others with it.
Set a buried course of blocks under the first step, as for a wall.
Risk of falls, especially on ice, and a non-compliant stair at a house entrance.
Beyond three risers at an entrance, plan a handrail; if the surface is more than 600 mm above the ground beside it, a guard.
These steps serve the house entrance: the code rules apply (uniform rises, run, width, handrail, guard). Have the plan checked if in doubt.[1, 7]
With about four risers or more at an entrance, a handrail is generally required. Check your municipality's rule.[7]
Above about 600 mm of total rise, a walking surface or landing may need a guard, which must be solidly anchored: have it designed or installed by a professional.[19]
Steps attached to the building or on concrete footings fall outside the RBQ exemption: hire a business holding the right licence.[6, 20]
File a free Info-Excavation request at least 4 business days before you dig.[9]
Block or paver landings and steps set on gravel that serve an entrance without being attached to the building need no RBQ licence. Attached steps or steps on concrete footings belong to a licensed business (interpretation, to confirm with the RBQ for your case).[6]
Checked October 10, 2026
For a stair serving a dwelling, the National Building Code 2020 values summarized by CCOHS are: rise 125 to 180 mm, run 255 to 355 mm, width at least 900 mm, handrail 865 to 1,070 mm high, uniform steps. The Quebec Construction Code edition in force remains to be confirmed.[1]
Checked October 10, 2026
Boucherville: the construction bylaw allows rises up to 216 mm for certain existing exterior stairs. An example of a local rule that changes the code.[8]
Checked October 10, 2026
Before digging, even a small footprint, file a free Info-Excavation request at least 4 business days ahead.[9]
Checked October 10, 2026
Escaliers : prévention contre les chutes · Centre canadien d'hygiène et de sécurité au travail (CCHST)
Consulted October 10, 2026Source page
Guidance for the construction of domestic steps, V1.0 · Tobermore
Consulted October 10, 2026Source page
CUGE Research Technical Note 02-2009: Steps in the landscape · National Parks Board (Singapore)
Consulted October 10, 2026Source page
Experience curve effects · Wikipedia
Consulted October 10, 2026Source page
Guide produit : marche Celtik · Permacon
Consulted October 10, 2026Source page
Guide pour déterminer le besoin d'une licence et la sous-catégorie pertinente : sous-catégorie 2.7, Entrepreneur en travaux d'emplacement · Régie du bâtiment du Québec
Consulted October 10, 2026Source page
Garde-corps et main courante pour votre sécurité · CAA-Québec
Consulted October 10, 2026Source page
Règlement 2024-293-6 (construction) · Ville de Boucherville
Consulted October 10, 2026Source page
Travaux d'excavation · Régie du bâtiment du Québec
Consulted October 10, 2026Source page
Fiche technique 34, Protéger les services publics souterrains · APSAM (Association paritaire pour la santé et la sécurité du travail, secteur affaires municipales)
Consulted October 10, 2026Source page
Service de livraison · Gauvreau Transport
Consulted October 10, 2026Source page
Crushed stone (products and tonnage calculator) · Groupe Bellemare
Consulted October 10, 2026Source page
Guide des prix d'excavation : tout ce qu'il faut savoir · Soumission Rénovation
Published May 7, 2026Consulted October 10, 2026Source page
Basic Tech Guide / Project Planning Guide · Unilock
Consulted October 10, 2026Source page
Installation guide, Walls and design charts · Techo-Bloc (hosted by dealer Stonewood Products)
Consulted October 10, 2026Source page
Installation de pavé uni au Québec : guide complet des prix au m² et pi² · Soumission Rénovation
Consulted October 10, 2026Source page
Prix d'installation d'un mur de soutènement par un entrepreneur au Québec · Soumission Rénovation
Published August 19, 2026Consulted October 10, 2026Source page
DTNI-3C, Mise en oeuvre des pavés et des dalles en béton ou en pierre naturelle sur lit de pose granulaire · Ville de Montréal
Published October 3, 2024Consulted October 10, 2026Source page
Présentation : garde-corps (2025) · Municipalité de Roxton Pond
Consulted October 10, 2026Source page
Vérifier la licence d'un entrepreneur · Régie du bâtiment du Québec
Consulted October 10, 2026Source page
First version, written from the CCOHS code summary, the Tobermore and Unilock guides and the RBQ licence guide. Draft awaiting review by an installer.