Fiche technique S3-05 : fondations de béton (détail du nivellement et du drain)
APCHQ
Open the source- Consulted
- October 10, 2026
- Region
- QC
- Language
- fr
Cited by
What we take from it
- The APCHQ plans a 10% slope over 2 m along the foundation at backfill, which later settles to about 2%.
- The APCHQ detail covers the foundation drain with 150 mm of 19 mm clear stone.
- 10% slope over 2 m at backfill.
- Slope along the foundation and drain cover.
- The APCHQ recommends ground that moves water away from the foundation over at least 2 m: about a 10% slope before compaction, to end near 2% once the soil has settled.
- The APCHQ recommends ground that moves water away from the foundation over at least 2 m.