How much does low-voltage landscape lighting cost in Quebec?

For a typical project of 10 fixtures on 30.5 m (100 ft) of cable (all of Quebec): $1,952 doing it yourself, $1,400 to $2,100 by a contractor, before tax.

Outdoor fire pit and lit steps at dusk
Photo: Rinox

Prices follow the chosen region when it has observed prices; otherwise the province-wide value applies and the confidence grade drops.

Do it yourself or hire a contractor

Both columns come from the same engine, with the same quantities. The difference: labour, site-scale equipment, overhead and margin.

Do it yourself

Materials at retail prices, rentals, delivery and disposal, plus your time as a beginner (*).

$1,952

* Includes your time: 33.6 h × $35.05/h (beginner). Money spent only: $775

Before tax
Money spent only$775
GST (5%)$39
QST (9.975%)$77
Total with taxes$891

Tools to buy, on top: $42

By a contractor

Labour, equipment, materials, overhead and margin.

estimate
$1,400 to $2,100
Displayed range, before tax
Typical scenario$1,666
GST (5%)$83
QST (9.975%)$166
Total with taxes$1,915

Crew pace: 8 person-hours

Stacked extremes (everything low, everything high): $1,097 to $2,927

The range shows the effect of documented price and productivity spreads. It is not a probability.

Hiring costs less if your time is worth more than:

estimate
$27/h
Based on beginner hours.

At $35/h: hiring costs less.

Break-even = (the contractor's typical price minus the money spent doing it yourself) divided by your person-hours. Before tax on both sides: GST and QST apply to both.

Your time

Your time
2
$35.05/h
By default, the average hourly wage in Quebec:
Money, hours, days, value of the time and true cost, beginner and intermediate
MeasureBeginnerIntermediate
Money spent$775$775
Person-hours34 h23 h
Days of 8 h, 2 people2.5 days1.5 days
Your time at $35/h$1,177$814
True cost$1,952$1,589

Working days only: add rain days and waiting times (curing, deliveries).

True cost: money and time

Before tax, one scale for every bar.

Money spentYour time ($35/h)Contractor's rangeTypical price ($1,700)
Do-it-yourself true cost and a contractor's price, before tax
Money, do it yourself$775
True cost, beginner$1,952
True cost, intermediate$1,589
Contractor$1,400 to $2,100 ($1,700)
Adjust the dimensions in the estimator

Where the money goes

A contractor's typical price, split by category. The same split applies to the do-it-yourself total, without overhead or margin.
Split of the typical price before tax
Materials43%$717
Labour20%$333
Overhead27%$450
Margin10%$167
What moves the total
  • Contractor overhead: $1,499 to $1,908
  • Price: Low voltage LED path light: $1,592 to $1,907
  • Contractor profit: $1,499 to $1,809

The range shows the effect of documented price and productivity spreads. It is not a probability.

Difficulty, time and tools

Level

Intermediate

Estimated working time
Beginner34 person-hours
Intermediate23 person-hours

Hours for the typical project: the work calculation (a crew's pace times the level's factor, with rework, learning and unloading) plus the guide's planning and checks.

To rent

No rental needed for the typical project.

To buy
  • String and stakes
  • Wire stripper
  • Multimeter
When to call a pro
  • A new outdoor outlet is needed: that is work for a CMEQ electrician, and a homeowner may not do it themselves (RBQ).
  • A hard-wired transformer, or a timer wired to 120 V, must be installed by a CMEQ electrician.
  • Lighting near a pool or spa: special electrical rules apply. Have the system designed and installed by a CMEQ electrician.
  • Even a shallow slit is digging: file a free Info-Excavation request before opening the ground.Applies to the typical project

The five phases

Every project follows the same sequence. The guide details each step, with its times and quantities.
  1. 01

    Plan the lighting and size the system

    Start with safety (steps, paths, entrance), then accents (trees, walls, facade). Avoid glare for passers-by and neighbours: aim down or at the object you light.

  2. 02

    Who does what: electrician, homeowner and Info-Excavation

    The 120 V side is electrician's work. A new outdoor outlet, a new circuit, a hard-wired transformer or a timer on 120 V are electrical installation work: done for others, they are reserved to CMEQ members, which also covers lighting with its wires and devices. The RBQ states that a homeowner may not do their own electrical work, even in their own house.

  3. 03

    Open the slits and lay the cable

    Low-voltage cable goes in a narrow slit, under the lawn or mulch. The burial depth required in Quebec for 12 V cable has not yet been verified in our sources: follow the cable maker's instructions and ask the electrician who checks your outlet.

  4. 04

    Install the transformer

    A plug-in transformer mounts on the wall or a post near the outlet, at the height its manual gives. Each run's cable connects to the terminals of the chosen voltage tap (12, 13, 14 or 15 V depending on the model).

  5. 05

    Fit the fixtures, measure and adjust

    Fixtures connect to the cable with connectors made for burial. The fewer splices, the longer the system lasts: that is one advantage of hubs.

Rules in Quebec

What the law and municipalities require for this kind of work. Each line cites its source.
  • LicenceAll of Quebec

    Electrical installation work, lighting with its wires and devices included, is reserved to CMEQ members when done for others. A homeowner may not do their own electrical work, even at home: a new outlet, a circuit or a hard-wired transformer needs an electrician.

    Gouvernement du Québec (LégisQuébec)Régie du bâtiment du QuébecChecked October 10, 2026

  • LicenceAll of Quebec

    For a contractor installing only the 12 V side of a plug-in kit at a client's home, our sources do not settle the licence question. Ask the business whether it is a CMEQ member and check its licences before signing.

    Gouvernement du Québec (LégisQuébec)Régie du bâtiment du QuébecChecked October 10, 2026

  • SafetyAll of Quebec

    The Electricity chapter of the Construction Code adopts the Canadian Electrical Code with Quebec amendments. Choose equipment certified for Canada and plug the transformer into a GFCI-protected outdoor outlet.

    LégisQuébec, Éditeur officiel du QuébecChecked October 10, 2026

  • LocateAll of Quebec

    Before opening the ground for a cable or a spiked fixture, file a free Info-Excavation request.

    Régie du bâtiment du QuébecHydro-QuébecChecked October 10, 2026

  • Consumer protectionAll of Quebec

    Ask for a written contract detailing the fixtures, transformer, cable, the electrician's share, the total price and the warranty.

    Office de la protection du consommateurChecked October 10, 2026

Before you hire

Six questions to ask every contractor. A good quote answers them in writing, with numbers.
  1. 01

    Who makes the regulated connection?

    A CMEQ member electrician for anything on the 120 V side; a plumber for the potable water connection and backflow prevention.

  2. 02

    Where is the zone or circuit plan?

    A sketch with lengths, the number of heads or fixtures and the controller or transformer capacity.

  3. 03

    Exactly which equipment?

    The brand and model of each main part, so quotes can be compared with each other.

  4. 04

    How deep, and how under hard surfaces?

    Burial depth and sleeves under walkways and driveways.

  5. 05

    Start-up and seasonal service?

    Programming, adjustments, fall blowout and spring start-up: included or at what price.

  6. 06

    What warranty, in writing?

    On parts and on labour, with their duration.

In every case: an RBQ licence when the work requires one, a business number (NEQ), civil liability insurance and a written contract.

Guide: choosing a contractor

Sources and review

Draft: this content has not yet been reviewed by an installer or an engineer. The numbers come from the engine; the explanations may still change.

  • Last reviewed: October 10, 2026
  • Next review due: October 10, 2027
  • 13 sources cited