  • An estimated price may only rise for unforeseeable, justified work.
  • The Civil Code provides a one-year warranty against poor workmanship and five-year liability for loss of the work.
  • Before the contract, the contractor tells the client the nature of the work, the goods and the time needed; at an estimated price, an increase must be justified and unforeseeable; at a fixed price, the price does not change.
  • At a fixed price, the price does not change without agreement; at an estimated price, an increase must be justified.
  • The client accepts the work with or without reservations, need not pay before acceptance and may hold back enough to cover reservations; one-year warranty and five-year liability.
  • The Civil Code governs acceptance with or without reservations.
  • Estimated and fixed price rules.
  • Article 2107 on estimated prices.
  • Acceptance and holdback.
  • Civil Code of Quebec.
  • Contract for work: price, acceptance, warranties.
  • Civil Code text.
  • Article 979 of the Civil Code sets the rule of natural water flow between neighbouring lands.