  • Per the OIQ, height alone does not decide: a wall holding back soil falls under the Engineers Act if its design needs a study of its materials, depending on its function, the soil and loads above and below.
  • The OIQ lists the factors that make an engineer necessary: function, height, soil, erosion or slide risk, load above and loads below the wall.
  • The OIQ counts the load above the wall among the factors that require an engineer; municipal thresholds do not replace the Act.
  • The OIQ counts erosion or slide risk among the factors.
  • The OIQ counts the soil type among the factors.
  • The OIQ counts erosion among the factors that require an engineer.
  • The OIQ cites tiered walls of about 2 m each built without an engineer among the cases covered by the Act.
  • OIQ position on retaining walls.
  • When an engineer is required.
  • The OIQ points out that height alone does not decide, but a retaining wall carries soil load.
  • For the OIQ, height alone does not decide whether a retaining wall needs an engineer: the slope above, the soil, the surcharge and the slide risk count too.